Community Development

The objective of the Community Development Department is to guide the development of the County through effective measures of planning, design review, construction plan approval, code compliance, and environmental health to preserve and enhance the quality of life for the residents of La Paz County.


Community Development Fee Schedule

La Paz County GIS

Flood Plain Ordinance: FCD 2010-01

Request for Public Record(s)--Online Form

Request for Public Record(s)--Download Version



Contact Us:

Community Development

Physical Address
1112 S Joshua Avenue
Parker, AZ 85344

Phone: 928-669-6138

Hours

Monday - Thursday
7:00 AM - 6:00 PM

Closed Friday

Pursuant to A.R.S. 48-3645, La Paz County establishes timeframes for which an Approval or Denial Statement will be issued for each type of permit that it reviews. The overall time frame for each type of permit states separately the administrative completeness review time frame and the substantive review time frame. These time frames include La Paz County’s review time and not the time the applicant takes responding to notices of deficiencies for either the administrative or substantive review.

Permit complexity type

Complexity general description*

Administrative Review (Working Days)

Substantive Review (Working Days)

Overall Time Frame (Working Days)

Complexity 1

Minimal technical review, single lot

20

40

60

Complexity 2

Multiple lots, average complexity

20

60

80

Complexity 3

Large projects with numerous lots, large acreage, large solar developments, subdivisions

30

75

105


*Please contact the Community Development Department to determine which complexity range your project falls in.

The times frames noted above reflect the maximum time allotted to complete the permitting process. Most permit applications submitted to the La Paz County Community Development department are quicker.

However, for your planning purposes, do not assume a faster time frame.